The New Shared Energy Storage Project in Yuanjiang County, Yunnan Province Successfully Completed the Installation of 20 PCS Cabins

on March 24, the new shared energy storage project in yuanjiang county successfully completed the installation of 20 PCS modules, and the project construction ushered in a key node.

As a key energy project in the Ganzhuang area of Yunnan Yuanjiang Industrial Park, the project will become an important support for the regional "source-network-load-storage" integrated new power system. The smooth installation of the 20 PCS cabins marks the successful fall of the "smart hub" of the energy storage system, laying the core foundation for subsequent energy conversion and grid peaking.

According to the construction plan, the remaining 39 battery compartments are expected to officially start lifting operations on April 10. The construction team plans in advance, scientifically deploys, refines the operation process, investigates potential safety hazards, and makes every effort to ensure the safe, accurate and efficient advancement of equipment hoisting. At the same time, the cable laying work in the energy storage area is being carried out. The construction personnel strictly follow the specification requirements, optimize the laying method, control the construction quality, effectively avoid the cable temperature rise and other problems, and ensure the efficient linkage between various equipment.

Since the start of the project, all the builders have overcome difficulties, fought day and night, strictly controlled the three barriers of project quality, safety, and progress, and coordinated the promotion of various construction tasks. At present, all links of the project work together and link up in an orderly manner, showing a good situation of "multi-point flowering and full speed promotion. In the next step, the project team will continue to anchor the target, press ahead with pressure, efficiently push forward the follow-up work such as battery compartment hoisting and cable laying, spare no effort to seize the construction period, ensure quality and promote production, strive to play the important role of peak shaving and valley shaving and stabilizing the power grid as soon as possible, and inject strong green kinetic energy into the high-quality development of energy in Yuanjiang region.