as the core sub-project of "storage" in our county's "source network, load and storage" integration project, the project is jointly constructed by Shanxi Zhongsheng Wisdom Power Co., Ltd. and Shanxi Zhixian New Energy Co., Ltd., with a total investment of 0.206 billion yuan. It is planned to build a hybrid energy storage station integrating lithium-ion batteries and super capacitors. Among them, the installed scale of lithium-ion battery is 32.5MW/130MWh, and the installed scale of super capacitor is 10MW/0.083MWh.
at present, 26 energy storage battery compartments and 7 PCS boost inverter integrated compartments have all been present and installed in place. The construction founder is concentrating its efforts to step up the installation of super-capacity integrated warehouse and secondary equipment.
"At present, the civil engineering of the project has been completed, and the energy storage equipment and lightning rod equipment have also been installed. Super capacity equipment and booster station equipment are being deployed to the scene one after another to step up construction operations. It is expected to be completed by the end of March and enter the commissioning phase." Feng Yanshan, head of the project equipment installation, said.
at present, the participating parties are keeping a close eye on the target of "commissioning at the end of March", wall chart operations and inverted construction periods. on the premise of ensuring construction safety and project quality, they are racing against time to seize the construction period and make every effort to grasp the progress.