on March 19, the ecological environment bureau of Ningde city, Fujian province issued a public announcement on the approval and acceptance of the environmental impact report (form) of the Datang fu' an xiwei 80MW fishing and light complementary photovoltaic power station project.
according to the public announcement, the project is located in Xiapi village aquaculture pond, xiwei town, fu an city, Fujian province. it is planned to use the space above the aquaculture pond to build a centralized photovoltaic power station with an installed capacity of

Datang (fu an) new energy co., ltd. is responsible for the construction.
the construction content of the project includes grid-connected equipment such as photovoltaic DC array, energy storage equipment (equipped with a set of 8MW/16MWh electrochemical energy storage system) and 35kV collector line.
The annual new generation capacity of the project is 118.86474 million kWh.